Helloshabby.com -- If you're working abroad, of course the first thing on your mind is to build a house so that your family is more comfortable and it can be the result of your hard work that is fully realized. This time we provide home inspiration from workers in Singapore that you can use as motivation. Check out Singapore OFW - Simple House with Cost Detail.
House exterior
The house has an ideal structure with a safe elevation for low-lying areas. The minimalist house concept is combined with a shed-type roof that has a clean design. The addition of a pitched roof on the porch is a more interesting touch and makes it more shady so that the porch can become a functional space by adding some furniture in it.
Interior view
Entering the house, the room is made open space which makes the impression more spacious and airy. The front part can be used as a guest area by adding a sofa with a harmonious design. Large windows also occupy many spots so that the house feels more open and brighter.
Kitchen
The kitchen is at the back of the room, with the bar counter added as a cover to make it more private. The design of the kitchen table is made lower compared to the bar table to be more hidden. In addition, the owner also added a nice pattern for the tile so that it looks classy and clean.
Bathroom
The bathroom is small and has an additional curtain to separate the shower and toilet area. The room itself uses a white color that makes the impression more spacious and the lighting can be evenly distributed.
Cost detail
BUILDING THE HOUSE 1,218,716 PHP
$24,374 USD with Labor
PLAN WITH BUILDING PERMIT = 15,000
STRUCTURAL = 326,972
STEEL TRUSSES = 54,535
ROOFING = 55,200
SPANDREL = 23,125
PORCH & CANOPY WINDOW = 21,905
PLASTERING AND ECT.... 7,880
Septic Tank & Toilet Pipe = 14,091
Flooring = 33,544
Electricity = 59,545
Plastering = 93,930
Glass Windows & Doors = 61,090
Other Expenses Door Jamb = 7,920
Materials Kitchen Sink Counter Top,Toilets Tile and Accesories = 87,916.85
Labor 7days = 22,650
Snacks = 2,292
Fare Materials Lunch and Snack = 4,061
TOTAL COST = 116,919.85
Hanging Cabinet,Under Lavatory
in Toilet Master = 3,200
Glass Door and Shower Enclosure Master = 7,000
Accesories Toilet Installation = 2,240
Snacks/Lunch Installation Accesories toilet and door,Master Toilet = 1,547
TOTAL COST =13,987
Municipal Occupancy Permit = 3,900
Requirements Fire Extinguisher = 2,800
Fare and Snack = 770
TOTAL COST = 7,470
INEC CONTADOR = 2,143.49
Doors of 3rooms and 1toilet door
1hamba toilet with Labor = 30,000
Black Compressor = 1,500
TOTAL COST = 31,500
Ceiling Materials = 37,911
Labor Contract = 22,000
TOTAL COST = 59,911
Materials Tiles Living to Kitchen,
Rooms,Porch and Fare = 66,073.30
Labor Contract = 22,750
TOTAL COST = 88,823.30
Paint Materials = 38,362
Labor Contract = 40,000
TOTAL COST = 78,362
Added Electricity Materials = 7,788
Lights = 31,892.06
Labor Installation Lights = 3,700
TOTAL = 43,380.06
OTHER EXPENSES = 1,483
Start Building A House November 28 2019
House Size 7 x 10.5 meter
73.5sqmeter 3rooms 2Toilet&B,Terrace,Living,Dining,Kitchen
Qty Item Price/Unit Total
100bags -Holcim Cement -235 = 23,500
5load -Sand/Balas -1,800 = 9,000
2,000pcs - #5 Hollow Block - 13 = 26,000
150pcs - Roundbar 10mm - 117 = 17,550
24pcs - Roundbar 12mm - 169 = 4,056
110pcs - Roundbar 16mm - 299 = 32,890
48pcs - Coco Lumber 2x2x12 - 212 =10,176
20kilos -Tie Wire = 1,400
10kilos - #4 C W Nails = 900
10kilos - #3 C W Nails = 700
5kilos - #2 C W Nails = 350
First Order = 126,322
Qty Item Price/Unit
1bag Holcim Cement 235 pesos
Qty Item Price/Unit
1pc 16mm Roundbar 299 pesos
1pc 12mm Roundbar 169 pesos
1pc 10mm Roundbar 117 pesos
Qty Item Price/Unit
1pc Wood 212 pesos
Qty Item Price/Unit
1pc Ordinary Plywood 680 pesos
STEEL TRUSSES MATERIALS
Qty Items Unit/Price Total
15pcs - Channel 4" - 1,480 - 22,200
28pcs - C-Purlins 2x3 (1.5) - 500 - 14,000
8pcs - C-Purlins 2x8 (1.5) - 830 - 6,640
4pcs - AngleBar 3/16×1 1/2 - 340 - 1,360
1Gal - Epoxy Red - 750 - 750
1Gal - Epoxy Red - 640 - 640
1Gal - Epoxy Red - 780 - 780
2Litter - Epoxy Red - 190 - 280
1Gal - Thinner - 250 - 250
1Gal - Tninner - 180 - 180
4Litter - Thinner - 45 - 180
2pcs - P-Brush 2×1/2 - 50 - 100
4pcs - P-Brush 2 - 35 - 140
4pcs - Darie 4" CD - 35 - 140
2pcs - Toka CD - 200 - 400
2pcs - Sand Flex 18+ - 60 - 120
1pc - Freight - 500 - 500
TOTAL COST = 48,760
Steel Trusses Materials =48,760
Steel Trusses Labor Cost =4,900
Painting for Trusses Labor Cost = 870
TOTAL COST = 54,535
ROOFING MATERIALS MATTE GRAY
Qty - Item - Unit/Price - Total
110.4LM - TERRARIB 0.45 - 616.94 - 68,110.18
7pcs - Box Gutter 0.45 - 865.55 - 6,058.85
15pcs - End Flashing 0.45 - 865.25 - 12,983.25
700pcs - Tekscrew 12x65 - 1.25 - 875
600pcs - Blind Rivets - 0.40 - 240
3pcs - Silicone Sealant - 130 - 390
1pc - Touch Up Paint - 300 - 300
GROSS AMOUNT = 88,957.28
NET AMOUNT = 41,621
LABOR.
DELIVERY CHRAGE = 10,000
TOTAL CONTRACT AMOUNT = 51,621
CLOSED C = 50,000
Roofing Materials Cost = 50,000
Labor Cost = 5,200
TOTAL COST = 55,200
MATERIALS SPANDREL = 17,000
LABOR COST = 6,125
TOTAL COST = 23,125
Pag Hukay para sa Septic Tank...Labor Cost 1,750 Pesos
Septic Tank
Materials = 8,220
Labor = 3,375
Car Rent = 2,500
TOTAL = 14,095 PHP
Flooring....
Materials = 24,274
Labor = 8,625
Snacks = 645
TOTAL = 33,544 PHP
Electricity...
Materials = 44,816
Labor = 13,420
Snacks = 959
Materials Fare = 350
Total = 59,545
3pcs - Hamba Door - 2,000 - 6,000
1kl - Nail - 70 - 70
TOTAL = 6,070
Plastering
Materials = 39,810
Labor = 51,525
Snacks = 2,218
Materials Fare = 377
Total = 93,930 PHP
Windows and Doors
Labor Materials = 60,000
Snacks = 455
Primer Materials = 635
Total = 61,090 PHP
TOTAL COST 1,218,716 PHP
$24,374 USD with Labor